(Surface 3-1/2 days, Subsea 4 days)
DAY 1
- Introduction
- Introduction to Course & Facilities
- Importance of Well Control
- Definition of Kick and Blowout
- Possible Costs of a Blowout
- Well Control Philosophy
- Well Control Basics
- Basic Concepts
- Hydrostatic Pressure
- Formation Pressure
- Overburden Pressure
- Fracture Pressure
- Bottom-Hole Pressure
- Pump Pressure
- Surge and Swab Pressure
- Shut-In Drill Pipe Pressure
- Shut-In Casing Pressure
- Basic Calculations
- Capacity
- Displacement
- Pump Outputs
- Fluid Weight Up
- Others
- Causes of Kicks
- Failure to Keep the Hole Full
- Swabbing
- Lost Circulation
- Insufficient Density of Fluid
- Abnormal Pressure
- Trip in Hole Too Fast
- Kick Warning
- Pit Gain
- Increase in Flow Rate
- Improper Fill on Trips
- Drilling Rate Change
- Decrease in Circulating Pressure
- Increase in Stroke Rate
- Mud Gas Content Change
- Gas Cut Mud
- Water Cut or Chlorides Change
- Sloughing Shale
- Well Flows with Pumps
- Change in Mud Properties
- Shut-In Procedures
- BOP, Choke, Diverter Controls
- Shut In While Drilling
- Shut In While Tripping
- Well Kill Procedures
- Drillers Method
- Wait & Weight Method
- Concurrent Method
- Reverse Circulation (Short Way)
- Killsheet Basic and Usage
- Taking Readings
- Strokes to Bit
- Kill Weight Mud
- Initial Circulating Pressure
- Final Circulating Pressure
- Decline Schedule
- Practice Problem
- Simulator Hands-On Practice
- Slow Pump Pressure
- Kick Detection
- Shut-In Procedures
- Basic Kill Operation
- Individual Problems Session
- Written Question to Reinforce Material Covered
 |
DAY 2
- Review Session
- Well Control Instruction
- Equivalent Mud Weights
- Decline Schedules
- Friction Losses
- Casing Burst
- Well Control Mechanics
- Gas Bubble Migration
- Bleed Volumes for Gas Migration
- Excessive Annular Surface Pressure
- Gas/Oil/Water Kick Difference
- Abnormal Pressure Detection
- Geology & Development of Abnormal Pressure
- Penetration Rate Change
- Shale Density Change
- Mud Chloride Change
- Shale Cuttings Change
- Mud Gas Content Changes
- Simulator Hand-On Practice
- Kill Sheet Preparation
- Slow Pump Pressure
- Kick Detection
- Shut-In Procedures
- Advanced Kill Operation
- Individual Problems Session
- Basic Calculations
- Equivalent Mud Weights
- Casing Seat Tests
- Casing Burst Limitations
- Kill Sheet Calculations
- Kill Operation Procedures
DAY 3
- Review
- Drilling Fluids
- Density
- Viscosity
- Fluid Loss
- Salinity
- Gas-Cutting
- Mud Weight-Up
- Completion and Workover Fluids
- Functions of Fluids
- Well Control
- Cleaning Out a Well
- Plugging Back
- Bridging Agents
- Fluid Types
- Gases
- Water Base
- Oil Base
- Packer Fluids
- Fluid Properties
- Density & Temperature Offset
- Viscosity
- Density Increase
- Gas Cutting
- Fluid Loss
- Salinity
- Solids Content
- Gel Strength
- Crystallization
- Caustic Effect
- Shallow Gas Control
- Control of Shallow Gas Kicks
- Diverters
- Unusual Operations
- Drill Pipe is Off Bottom
- Drill Pipe is Out of Hole
- Lost Circulation
- Plugged Drillpipe
- Excessive Casing Pressure
- Hole In Drillpipe
- Special Techniques for Plugs
- Lost Circulation and Kill
- H2S Kicks
- Kicks During Snubbing, Coil-Tubing, & Small Tubing Operation
- Multiple Completions in Hole
- Hole in Casing String
- Strip & Snub In/Out of Hole Under Pressure
- Simultaneous Drilling, Workover, & Production Operations
- Running A Drill-Stem Test
- Perforating
- MMS Regulations and Worksheet
- Subpart D Drilling Operations
- Subpart G Plug & Abandonment
- Subpart C Pollution & Disposal
- Subpart E & F Completions & Workovers
- Well Control Equipment
- BOP & Diverter Equipment
- Installation
- Operation
- Maintenance
- Testing
- Equipment Limits, Pressure/Wear Instruction
- Auxiliary Equipment
- Pit Level Indicator
- Mud-Volume Measuring Device
- Mud-Return Indicator
- Gas Detector
- Trip Tank
- Mud-Gas Separator
- Degasser
- Adjustable Choke
- Closing Units
- Sizing and Maintenance
- Precharge Pressure
- Operating Pressure
- Usable Fluid Volumes
- Required Fluid Volumes
- Fluid Pumps
- Charging Fluid Maintenance & Inspection Procedures
- Other Well Control Equipment
- Surface Equipment
- Downhole Tools & Tubulars
- Packers
- Supervision of Kill Operation, Organizing & Directing Kill
- Individual Problem Session
Written Questions to Reinforce Material Covered
 |
DAY 4
- Review Session
- Written Exam ( Drilling Surface)
- Simulator Exam ( Drilling Surface)
- Special Subsea Considerations
- Choke Line Friction Determinations
- Use of Marine Risers
- Riser Collapse
- Gas in Top of BOP Stack
- U-Tube Effect as Gas Hits the Choke Line
- Subsea Exam
- Kill Sheet Preparation
- Simulator Exam
- Written Exam
- Reasons for Well Workovers
- Reworking an Existing Reservoir to:
- Increase Production
- Control Cuts
- Sand Control
- Formation Damage
- Re-Complete in Same Reservoirs
- Complete a New Reservoir
- Complete Multiple Reservoirs
- Stimulation
- Repair Mechanical Problems
- Preparing a Well for Entry
- Use of Back-Pressure Valves
- Surface and Subsurface Systems
- Removal of Tree & Tubing Hanger
- N/U & Test BOP
- Killing a Producing Well
- Bullheading
- Lubricate & Bleed
- Coil-Tubing Units
- Snubbing Units
DAY 5
- Individual Problems Session
- Written Questions to Reinforce Material Covered
- Workover Simulator Hands Practice
- Pump in Pressures
- Circulating Pressures
- Lubricate and Bleed
- Bullheading
- Simulator Hands-On Practice
- Kill Sheet Preparation
- Slow Pump Pressure
- Shut-In Procedures
- Reverse Circulation Kill (Producing Well)
- Simulator Hands On Practice
- Kill Sheet Preparation
- Slow Pump Pressure
- Kick Detection
- Shut-In Procedure
- Killing a Flow During Workover & Completion Operations
- Review
- Written Exam (WO/WC Surface)
- Simulator Exam (WO/WC Surface)
DAY 6
- Well Servicing Instruction
- Killing a Producing Well
- Coil Tubing Unit
- Snubbing Unit
- Special Tools
- Automatic Shut-Down Systems
- Control Points
- Activator Pilots
- Monitor Pilots
- Control Manifolds
- Subsurface System
- Downhole Tools & Tubulars
- Tubing Hanger
- Back-Pressure Valve
- Landing Nipples
- Locking Mandrels
- Gas Lift Equipment
- Running & Pulling Tools
- Flow String System
- Tubing
- Mandrels and Nipples
- Flow Couplings
- Blast Joints
- Sliding Sleeves
- Pumpdown Equipment
- Purpose
- Applications
- Requirements
- Surface Circulation System
- Lubricators
- Entry Loops
- Tree Connection/Flange
- Shut-In Procedures
- BOP System
- Subsurface Safety System
- Nitrogen Operations
- Applications
- Properties
- MMS Regulations
- Subpart H Emergency Shut Down Systems
- Subpart H Production Safety Systems
- Snubbing Operations
- Types
- Rig Assist
- Stand Alone
- Applications
- Run & Pull Prod. Or Kill String
- Reset Weight on Packer
- Fishing
- Circ. Cement or Fluid
- Equipment
- Operating Mechanism
- Power Supply
- Control Assembly & Basket
- Slip Assembly
- Mast & Counterbalance Winch
- Access Window
- BOP Equipment
- Tree Connection or Flange
- Rams
- Spool
- Traveling Slips
- Manifolds
- Auxiliary (Safety Valve, Inside BOP)
- Maintenance
- Testing
- Snubbing Exam
 |
DAY 7
- Coil-Tubing Operations
- Applications
- Initiating Flow
- Clean Out Operations
- Stimulation Operations
- Equipment Description
- Coil
- Tubing
- Reel
- Injection Head
- Control Assembly
- Injector Hoist
- BOP Equipment
- Tree Connection or Flange
- Rams
- Injector Assembly
- Circulating System
- Coil-Tubing Exam
- Wireline Operations
- Applications
- Equipment Description
- BOP Equipment
- Small-Tubing Operations
- Applications
- Stimulation Operations
- Clean Out Operations
- Plugback & Squeeze Cementing
- Equipment Description
- Derrick & Drawworks
- Small Tubing
- Pumps
- Weighted-Fluid Facilities
- Weighted-Fluids
- BOP Equipment
- Rams
- Wellhead Connection
- Check Valve
- Small-Tubing Exam
|
|